Week of January 17, 2011

College Park Center-Precast Erection Plan

Erection of the precast members at the seating area of the bowl will require the use of the tower crane along Pecan street. In order to hoist the precast risers, semi-trucks need to be brought in and staged adjacent to the project along the curb in the North bound lane of Pecan Street. Pecan street will be closed three times in the coming months.

The first lane closure will be set in place beginning at 6pm on Friday, January, 21, 2011. It will be set in place each evening at 6pm and removed each morning at 2:30am. The first lane closure is scheduled to be removed at 2:30am January 27, 2011.

The second lane closure will be set in place beginning 6pm on Monday, February 21, 2011. It will be set in place each evening at 6pm and removed each morning at 2:30am. The second lane closure is scheduled to be removed at 2:30 am, February 28, 2011.

The third lane closure will be set in place beginning 6pm on Monday,March 7, 2011. It will be set in place each evening at 6pm and removed each morning at 2:30am. The third and final lane closure is scheduled to be removed at 2:30 am, March 14, 2011.

Comments are closed