Week of April 12th, 2010

Pecan Street Overhead Update

We will be moving to Phase Three of the Pecan Street Project, Monday, April 19th.    Phase Three involves closing the Intersection at Pecan and Second and the first row of parking in the Arlington Hall lot. The intersection will only be closed for a few days, the row of parking could be closed for 10 days depending on weather.  Overflow parking will be allowed in lot 43 during this period if the Arlington Hall lot is full.  Signage will be placed at both entrances into the lot to notify students.

To insure students safety the entire construction site will be fenced off with chain link fencing secured to the pavement.  ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Ransom Hall Update

Construction continues and is currently scheduled for completion by June 30, 2010.

The departments will be moving into the building for occupancy the week of July 12, 2010.

Comments are closed