Week of October 25, 2010

Arlington Hall Chill Water Line Connection Project – Holiday Break Project

The contractor will begin mobilization on Wednesday, December 15th, setting up fencing and equipment.  None of the pathways or driveways will be blocked or closed until after December 18, 2010.  The project will be completed no later than Wednesday, January 12, 2011.

The scope of work will include closing the Arlington Hall circle requiring any foot traffic from Arlington Hall to Pecan Street or to the center of campus to use the south sidewalk from the building.  The circle and landscaping repairs will be completed before students return on January 14, 2011.

This project completes the chilled water loop from the basement of Arlington Hall  to the College Park District development.  We will also be installing an electrical conduit from the basement of Arlington Hall to the intersection of Pecan and Second for future electrical needs during large campus events, supporting both Residence Life and groups within the new center.