Week of November 8, 2010

Trinity House

The parking gate entrance is being relocated to allow for some parking lot improvements. The entrance will not be closed at any time; however,  it will be closed down to one lane at times during the project. The project will be completed with the next 10 days.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

West Street Sidewalk Improvements

A contractor is scheduled to extend the sidewalk on the west side of West Street. The new 5’ wide sidewalk will run from the West Street Bridge down to Doug Russell Rd. We ask that students not cross over the construction fencing along this path until the sidewalk is open for use.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Maverick Stadium Locker Room Renovations

Facilities Management is starting a renovation project to update the locker rooms and correct some ADA issues. The locker rooms will be closed from November 15, 2010 until shortly after the end of the semester.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Campus Trip Hazards

Facilities Management is working on repair and/or replacement of several sidewalks and entrances on campus to address trip hazards.  Please be aware of sidewalk closures signage and use caution in these areas were work is being done.  If special assistance is needed in these work area(s), please contact Facilities Management, the Police Department and/or the Office of Students with Disabilities.